Outdoor playground equipment for three residential communities in Malaysia

Selangor, Malaysia — Cedar Lane Community Management
Cedar Lane Community Management coordinated three separate outdoor play-area upgrades in Selangor. Each community selected one set: MHO-1020 for Site A, MHO-1018 for Site B and MHO-1014 for Site C. The project required site-specific layouts, retention of an existing tree and path at Site A, separate packing by site, and local installation and checks before opening on 28 June 2025.

COUNTRY / REGION
Malaysia — Selangor
RELATED PRODUCTS
Outdoor playground equipment; children’s jungle gyms
PROJECT PERIOD
10 February–15 July 2025 (initial enquiry through post-opening feedback)
SHIPPING METHOD
Ocean freight from Ningbo to Port Klang, followed by customer-arranged road delivery to each site

Procurement list

ПРОДУКТQUANTITYTIME
Outdoor Playground MHO-1020 — Site A1 setShipped: 16 May 2025; delivered to site: 10 June 2025
Outdoor Playground MHO-1018 — Site B1 setShipped: 16 May 2025; delivered to site: 10 June 2025
Outdoor Playground MHO-1014 — Site C1 setShipped: 16 May 2025; delivered to site: 10 June 2025
Payment schedule Deposit: payable after the contract was signed on 14 March 2025; received on 18 March 2025. Production required both receipt of the deposit and final drawing approval, completed on 21 March. Balance: payable after the agreed pre-shipment records were reviewed and accepted, before shipment release; received on 13 May 2025. All payments due under the contract were settled.

Communication records