Outdoor playground for a family restaurant in Cape Town, South Africa

Cape Town, South Africa · Harbour Table Kitchen

An independent 85-seat restaurant replaced occasional hired children’s activities with one permanent MHO-1020 outdoor play structure. The project retained a separate food-service route during phased courtyard works, closed a late colour-change request and rescheduled dispatch after the customer’s drain work was delayed.

COUNTRY / REGION
South Africa · Cape Town
RELATED PRODUCTS
MHO-1020 outdoor playground
PROJECT PERIOD
August 4, 2025 – January 12, 2026
SHIPPING METHOD
Ocean freight to Cape Town; local road delivery

Procurement list

PRODUITQUANTITYTIME
MHO-1020 outdoor playground1 setShipped October 17, 2025
Delivered December 1, 2025
Installed December 8, 2025
Payment schedule The deposit was payable after signing and was received on August 26, 2025. Production required deposit receipt and approval of the final drawings, confirmed on August 28. The balance was payable after acceptance of the pre-shipment documents and before dispatch; it was received on October 13. Dispatch also required the customer’s written release.

Communication records